Most Cincinnati suburbs ask one question about a new deck: does it meet code and clear the setbacks. Glendale asks a second one first, and the answer changes everything about how your project moves.
The village is a National Historic Landmark district, one of the earliest planned residential communities in the country. That designation is not ceremonial. It comes with a review process that applies to nearly all exterior work, and a deck is exterior work.
This guide covers how Glendale splits permitting into two separate paths, what the historic district review actually asks for, the one exception that lets a project skip it, and what all of that means if you are planning a deck on a Glendale lot.
The Village of Glendale
Glendale sits about fifteen miles north of downtown Cincinnati and covers roughly 1.7 square miles. It was incorporated in 1855, and the subdivision that became its historic core was laid out four years earlier, in 1851.
| At a glance | Village of Glendale, Building and Zoning Department |
| Address | 30 Village Square, Glendale, Ohio 45246 |
| Phone | (513) 771-7200 |
| The village | Incorporated 1855. Population about 2,155 across 1.7 square miles |
| What they handle | Building permits, zoning review, and Appropriateness Review inside the Historic District |
| Website | the village building and zoning department |
For a homeowner, the practical consequence is that the village takes exterior appearance seriously in a way most municipalities do not, and it has a standing commission to enforce that.
Location, Directions and Access
The Village offices sit at Village Square, in the middle of a village that is only about 1.7 square miles in total. Glendale is compact enough that once you are inside it, you are close to everything.
Address: 30 Village Square, Glendale, Ohio 45246. Phone: (513) 771-7200.
From Interstate 75
Take the Sharon Road exit and head west. Sharon Road runs west from the interstate into Glendale and meets Congress Avenue, which is State Route 747 and the main road running north and south through the village.
From Springfield Pike in Springdale
Springfield Pike is State Route 4, and it forms the western edge of the historic district. From Springdale, head east on Sharon Avenue, which runs from Springfield Pike over to Congress Avenue in Glendale.
Those two approaches come in from opposite sides, which is useful to know if you are trying to picture where the district boundary falls. The historic core sits roughly between Springfield Pike on the west and South Troy Avenue on the east, with Coral and Washington Avenues to the north and Oak Street to the south.
- Before you go. For a Historic District submission, bring the application, three bound sets of plans, a photo of the existing home or site, a site plan showing setbacks, and your materials description.
- Timing. The Planning and Historic Preservation Commission meets on the first Monday of the month at 5:30 p.m., and your submission is due at least seven days before that.
{Map Embed}
Two Permit Paths, One Village
Glendale divides the village into two areas for permitting purposes: inside the Historic District boundary, and outside it. Which side your property falls on determines the entire process.

The district covers roughly 392 acres, bounded broadly by Coral and Washington Avenues to the north, Springfield Pike to the west, Oak Street to the south, and South Troy Avenue to the east. Those are rough edges rather than a legal description, and the village publishes a boundary map.
If you are not certain which side you are on, that is the first phone call to make. It costs nothing to ask and it determines your timeline.
What the Historic District Review Requires
Inside the district, exterior work goes to the Glendale Planning and Historic Preservation Commission for what the village calls an Appropriateness Review. The commission is made up of planners, architects, and people with historic preservation expertise, and it works from the village’s own Historic Design Guidelines.
The submission is more demanding than a standard permit application. You provide:
- A completed application
- Three complete and bound sets of building plans, showing all sides of the exterior project with design and dimensions
- A photograph of the existing home or building site
- A site plan indicating front, rear and side yard setbacks
- A description of the building materials you intend to use
Note the material description. In a standard permit review nobody asks what species of wood you are using or what the railing is made of. Here it is part of the application, because the commission is evaluating whether the project suits the architecture around it.
- Submit seven days early. The village asks for the completed application and designs at least a week before the meeting, so the commission has time to review them properly.
- The commission meets monthly. First Monday of the month, at 5:30 p.m. Miss the submission window and you are waiting for the next one.
- Plan around the calendar. This is the single biggest scheduling difference from a neighboring city. Your project timeline is set by a meeting date, not by how fast a reviewer works.
The One Exception: Like and Same
There is a narrow way out of Appropriateness Review, and it is worth understanding precisely because it is narrower than people hope.
Projects that replace like with same, meaning no change in material and no change in architecture, can be exempted. The Village Administrator decides whether a project meets that condition.
For decks, this rarely applies. Replacing a rotted board on an existing deck with the identical material is like and same. Building a new deck, enlarging an existing one, or rebuilding in a different material is not. If you are adding outdoor living space, assume review applies and be pleasantly surprised if it does not.
What This Means for a Deck
Put the two paths together and the practical picture for a Glendale deck looks like this.
Outside the district, the process resembles a typical Ohio village. Zoning review happens first, then the application goes to the Building Department for plan review and approval. The village contracts a registered architect as its Chief Building Official, who issues permits and performs inspections. Roughly a hundred residents apply for building permits in Glendale each year, so this is a well worn path.
Inside the district, add the commission. Add three bound sets of drawings instead of one. Add the material description and the site photo. Add the seven day lead time and the monthly meeting. None of it is unreasonable, but all of it takes planning, and a homeowner who discovers it after ordering material has a problem.
The design consequence is worth naming too. A deck that would pass without comment in a subdivision may draw questions here if the railing style, the material, or the visible massing sits awkwardly against a Victorian or Greek Revival facade. Working with the architecture rather than against it is both the faster path through review and, honestly, the better looking result.
Planning a Deck in an Older Community
Glendale is unusual in the strength of its review, but it is not alone in having a layer above the building code. Across the north and east side of the metro, plenty of homeowners answer to something beyond the city: a homeowners association, a zoning overlay, a set of deed restrictions on an older plat.
The mechanics differ but the lesson repeats. In a nearby village with its own historic character, zoning overlays in a historic village setting shape what can be built and how it must look. In an established older suburb, another established community’s permit path runs through a city process with its own timing.
In master planned neighborhoods the gatekeeper is private rather than municipal, and getting community association sign off first comes before the city ever sees the plan. Elsewhere the binding constraint is dimensional, where property line limits in a nearby community decide the footprint before anyone discusses appearance.
Platinum Deck and Patio builds across all of these jurisdictions, and in a place like Glendale most of the work happens before construction: reading the guidelines, drawing something that belongs on the street it is going on, and getting it in front of the commission with time to spare.
Frequently Asked Questions
Do I need a permit for a deck in Glendale?
Yes. A deck is exterior work, and building permits in Glendale are obtained through the village. If the property sits inside the Historic District, the project also requires Appropriateness Review by the Planning and Historic Preservation Commission.
How do I find out if my house is in the Historic District?
Call the Village office at (513) 771-7200. The village also publishes a boundary map. This is worth confirming before you spend anything on design, because it determines your entire process.
How long does historic district review take?
The commission meets on the first Monday of each month, and your completed application and designs are due at least seven days beforehand. Plan on scheduling around that calendar rather than a rolling review.
How many sets of plans do I need?
Three complete and bound sets for a Historic District submission, showing all sides of the exterior project with design and dimensions, plus a site plan, a photo, and a materials description.
Can I skip the review if I am just replacing an old deck?
Only if the work qualifies as like and same, meaning no change in material and no change in architecture. The Village Administrator makes that determination. A straight rebuild in a different material does not qualify.
Does the commission care what my deck is made of?
Yes. A description of the building materials is part of the application, and the commission reviews projects against the village’s Historic Design Guidelines. Material and style are part of what is being evaluated, not just dimensions.
The Bottom Line
Glendale asks more of a deck project than its neighbors do, and the reason is a good one. The village has protected an unusually intact nineteenth century streetscape for a long time, and the review process is how it keeps doing that.
The practical next step is a single phone call to confirm whether your address falls inside the district boundary. That one answer tells you whether you are looking at a standard permit or a commission submission, and everything downstream depends on it.
If you are inside, build the calendar into your plan from the start. Design something that suits the house, get three bound sets together, and file with a week to spare. Projects that respect the process here tend to move through it without much friction.